Internal Work · Toilet - Flush tank (concealed) fixing work is in progress for toilets
External Work
Brickwork in South side balcony and concreting work in the same area for Elevation is in progress
External putty work is progress in East and South side
Elevation plastering work is progress in West sides
Laying of clay tiles for Weathering proof over surki concrete is completed
Plumbing shaft pipe line work is in progress
BLOCK V
External Work
Brick work is progress for Elevation work in North side
Elevation plastering work is progress in West sides
Plastering work inside the Open to Sky (OTS) area is completed
CLUB HOUSE
Ground Floor
Internal plastering work is completed and curing work is in progress
First Floor · Brick work is in progress.
SEWAGE TREATMENT PLANT (STP)
Internal plastering for RCC wall work is in progress.
Roof slab shuttering work is in progress
AUGUST -2020
BLOCK - I
Fourth Floor · Internal putty work is completed.
External Work · South side balcony brick work and concreting work for elevation is in progress. · Brick work and Plastering work are in progress on Eastern side for elevation.
External Work · South side balcony brick work and concreting work for elevation is in progress. · Brick work and Plastering work are in progress on Eastern side for elevation.
BLOCK -V
Second Floor · Water proofing work for toilets is completed.
Third Floor · Internal Putty work is in progress.
External Work · Plastering work for the Lift and Open to Sky (OTS) area is in progress and the same for external areas to be commenced.
CLUB HOUSE
Ground Floor · Electrical wall cutting work and Laying of electrical pipe line work is in progress. · Internal plastering work is in progress.
Second Floor · Casting of second floor roof slab work is completed and curing work is in progress.
SEWAGE TREATMENT PLANT (STP)
RCC wall concreting up to 8'6" height is completed and steel shuttering work for the next level is completed. Concreting is scheduled on 07th September.
JULY-2020
BLOCK -1
Fourth Floor · Internal putty work is in progress. · Laying of pipe lines inside toilets is in progress
External work · South side balcony brick work and concreting work for elevation is in progress. · North side plastering work is completed. · Brick work is in progress on Eastern side for elevation.
BLOCK -5
Second Floor · Ceiling Plumbing line laying work (suspended plumbing works) inside the toilets is completed.
Third Floor · Internal plastering work is completed for flats and the same for corridor areas to be commenced.
Fourth Floor · Internal plastering work is in progress.
CLUB HOUSE
Ground Floor · Electrical wall cutting work and Laying of electrical pipe line work is in progress. · Internal plastering work is in progress.
Second Floor · Roof slab shuttering work is in progress.
SEWAGE TREATMENT PLANT (STP)
RCC wall concreting upto 3'0" height is completed and Fabrication of steel work and shuttering work is in progress for the remaining area.
JUNE -2020
BLOCK : 1
Third Floor · Internal and corridor area putty work is completed.
Fourth Floor · Internal plastering work for 7 flats is completed and the same for remaining flat and corridor work is in progress.
External work · 3 Nos of OTS area (Open To Sky) plastering work is completed. · OTS area (Open To Sky) white washing work is in progress. · South side balcony brick work and elevation work is in progress. · Plumbing work inside the shaft area is in progress.
BLOCK : 5
First Floor · Ceiling Plumbing line laying work (suspended plumbing works) inside the toilets is completed.
Second Floor · Internal Putty work is completed.
Third Floor · Internal plastering work is in progress
Fourth Floor · Laying of Electrical pipeline work is completed. · Internal plastering work is in progress.
Terrace Floor · Over Head water tank wall concreting work is completed. · Laying of weathering course with lime surkhi concrete is in progress.
CLUB HOUSE
Second Floor · Column concreting upto second floor roof is in progress.
SEWAGE TREATMENT PLANT
Earth work excavation work is completed. · Plain Cement concreting work is completed. · Footing concreting work is completed. · Consolidation work is in progress.
MAY -2020
BLOCK - I ;
First Floor • Water Proofing work is completed in toilets.
Second Floor • Water Proofing work is completed in toilets. • Entrance Door frames and bed room door frames fixing work is completed
Third Floor • Entrance Door frames and bed room door frames fixing work is in progress. • Ceiling Plumbing line laying work (suspended plumbing works) inside the toilets is completed. • Plumbing wall cutting and pipeline laying work in toilets is completed.
Terrace Floor Laying of Weathering course with surki lime concrete is in progress.
BLOCK : V
Ground Floor (Car parking Area) • Putty work is in progress.
CLUB HOUSE
Ground Floor: • Brick work is in progress
First Floor • Casting of (16 Feet height) roof slab concrete is completed and curing work is in progress.
Second Floor • Column concreting upto second floor roof is in progress
APRIL - 2020 - LOCKDOWN
MARCH 2020
BLOCK : I
Stilt Floor
White washing for ceiling and columns is completed and Putty work for ceiling is completed.
First Floor
Plumbing line laying work inside the toilets is in progress.
Second Floor
Plumbing line laying work inside the toilets is in progress.
First coat of putty work is completed
Third Floor
Internal plastering work is in progress
First coat of putty work is completed in four flats
Fourth Floor
Wall cutting work for laying electrical pipe line is in progress
Laying of Electrical pipe and fixing metal box work is in progress
BLOCK - 5
First Floor
First Floor - Internal Plastering work is completed.
Second floor - Internal plastering work is in progress
Third Floor - Wall cutting and laying of electrical pipe line work is completed
Fourth Floor - Brick work up to roof level is completed.
Terrace - Brick work for Parapet Wall is completed.
Shuttering and fabrication of steel for Staircase Head room is in progress.
BLOCK : II
Grade beam concreting work is in progress
Raising of Columns upto stilt floor roof level is in progress
Brick Work upto Basement level is in progress
Refilling inside the basement and consolidation work is in progress
Laying of Plain cement Concrete for flooring is in progress
Club House
Ground Floor - Brick work is in progress. - Lintel concreting work is in progress.
First Floor - Casting of First floor roof slab (upto 14 feet height first level) is completed and curing work is in progress. - Wall concreting for swimming pool is completed and curing work is in progress.
Second Floor - Raising of Columns upto second floor roof level is in progress
FEBRUARY -2020
BLOCK : I
First Floor - Plumbing line laying work inside the toilets is in progress. First coat of putty work is completed
External Elevation work is in progress
Second Floor - First coat of putty work is completed
Third Floor - Internal plastering work is in progress
BLOCK :V
First Floor - Internal Plastering work is completed
Second floor -Internal plastering work is in progress
Third Floor - Wall cutting and laying of electrical pipe line work is in progress
Terrace - Brick work for Parapet Wall is in progress
BLOCK :II
Column footing work is fully completed
Grade beam concreting work is in progress
Raising of Columns upto stilt floor roof level is in progress
Brick Work upto Basement level is in progress
CLUB HOUSE
Ground Floor - Brick work is in progress.
First Floor - Shuttering and fabrication of steel work for roof slab is in progress
Kindly note that Concreting of first floor roof slab is scheduled on 4th March 2020
JANUARY- 2020
BLOCK-I
• First Floor - Wall plastering work is completed. Plumbing line laying work inside the toilets is in progress
Second Floor - Electrical Box fixing work is completed and internal plastering work is in progress
Third Floor - Wall cutting and laying of electrical pipe line work is in progress.
Fourth Floor - Brick work upto roof level is completed
Terrace - Parapet Wall brickwork is completed. Shuttering and fabrication of steel for lift room and staircase head room is in progress.
BLOCK- V
First Floor - Wall Plastering work is completed
Second Floor - Electrical Box fixing and Internal plastering work is in progress
Fourth Floor - Lintel concreting work and brick work above lintel is in progress.
Terrace - Brick work for Parapet Wall, Lift and staircase head room is in progress
BLOCK -II
• Ground Level - Refilling of soil and consolidation work inside column footing pit is in progress
Brick on edge for grade beam is in progress.
CLUB HOUSE
Ground Floor - Casting of Ground floor roof Slab is completed and curring work is in progress.
First Floor - Raising of Columns upto first floor roof level is in progress
AUGUST 2019
BLOCK:I
Casting of Fourth Floor roof slab (terrace floor) is completed and curing work is in progress
Brick work in First floor is completed in all flats
Brick work up to lintel level in second floor is in progress
Ceiling and column plastering in stilt floor (Car parking) is completed
BLOCK:V
Column concreting for 49 Nos is completed in fourth floor, Fabrication of steel is completed for the remaining columns and shuttering work for the remaining columns in fourth floor is in progress
50% of shuttering and fabrication of steel work for fourth floor roof slab is in progress
Brick work up to Lintel level in First floor is completed in all flats and Brick work above lintel level is in progress in two flats after casting of lintel concrete
Ceiling plastering in stilt floor (Car parking) is in progress
CLUB HOUSE
Earth work excavation is completed for column footings
Laying of foundation concrete in Plain Cement concrete for footings is completed
Laying of RCC Footing for Column is completed
INFRASTRUCTURE
Perimeter Compound wall work is in progress
JULY 2019
BLOCK:I
Column concreting for 56 Nos is completed in fourth floor and Fabrication of steel and shuttering work for the remaining columns in fourth floor is in progress.
50% of shuttering work for fourth floor roof slab is completed and fabrication of steel work is in progress.
Brick work up to Lintel level in First floor is completed in all flats and Brick work above lintel level is in progress in two flats after casting of lintel concrete.
Fabrication of steel and shuttering work is in progress for casting of lintel for remaining flats in first floor
Brick work in second floor is in progress
Ceiling plastering in stilt floor (Car parking) is in progress
BLOCK: V
Casting of Third Floor roof slab is completed and curing work is in progress.
Brick work in First floor is in progress
CLUB HOUSE
Earth work excavation is completed for column footings
Laying of foundation concrete in Plain Cement concrete for 26 footings is completed and work is in progress for the remaining footings.
Laying of RCC for Column footing is completed for 16 columns and fabrication of steel for remaining footings and columns work is in progress.
INFRASTRUCTURE
Perimeter Compound wall work is in progress
JUNE-2019
BLOCK:I
Casting of Third Floor roof slab is completed and curing work is in progress
Brick work up to Lintel level in First floor is in progress.
BLOCK:V
Column concreting for 47 Nos is completed in third floor and Fabrication of steel and shuttering work for the remaining columns in third floor is in progress.
Third floor roof slab shuttering and fabrication of steel work is completed and laying of electrical pipe work is in progress for the 50% of slab area. Concreting is scheduled on 2nd July.
Shuttering work is in progress for the remaining 50% area
CLUB HOUSE
Earth work excavation is in progress
INFRASTRUCTURE
Perimeter Compound wall work is in progress
MAY -2019
BLOCK :I
Column concreting is completed in third floor.
Third floor roof slab shuttering work and fabrication of steel work is in progress for the 50% of slab area and Concreting is scheduled for Coming week.
Marking of brick work in First floor is in progress.
BLOCK :V
Second Floor roof slab curing work is in progress
INFRASTRUCTURE
Perimeter Compound wall work is in progress
APRIL -2019
Block I:
Casting of Second Floor roof slab is completed and curing work is in progress.
BLOCK :V
Second Floor roof slab curing work is in progress
INFRASTRUCTURE
Perimeter Compound wall work is in progress
APRIL -2019
Block I:
Casting of Second Floor roof slab is completed and curing work is in progress.
Block V:
Casting of First Floor roof slab is completed.
Fabrication of steel work for columns in second floor is in progress.
Infrastructure
Perimeter Compound Wall work is in progress.
SEPEMBER-2019
BLOCK :I
Brick work up to lintel level in Third Floor is in Progress
Brick work up to lintel level in second floor is completed
Brick work in First floor is completed in all flats
Ceiling plastering work in First floor is completed
Laying of Electrical pipe and fixing metal box work in First floor is in progress
Ceiling and column plastering work in stilt floor (Car parking) is completed.
BLOCK : V
Casting of Fourth Floor roof slab (terrace floor) is completed
Brick work up to Lintel level in Third floor is in progress
Brick work up to Lintel level in second floor is in progress
Brick work in First floor is completed in all flats
Ceiling plastering work in First floor is in progress
Laying of Electrical pipe and fixing metal box work in First floor is in progress
Ceiling plastering in stilt floor (Car parking) is completed
CLUB HOUSE
Earth work excavation is completed for Grade beam
Fabrication of steel work for grade beam is in progress
Column concreting up to grade beam level is completed
INFRASTRUCTURE
Perimeter Compound wall work is in progress
OCTOBER - 2019
BLOCK - I
Brick work up to lintel level in Second and Third Floor is completed
Brick work upto lintel level in Fourth floor is in progress
Ceiling plastering work in First floor is completed
Laying of Electrical pipe and fixing metal box work in First floor is in progress
Wall plastering work in First floor is in progress
Ceiling and column plastering work in stilt floor (Car parking) is completed
BLOCK - V
Brick work up to Lintel level in Second and Third floor is in progress
Brick work in First floor is completed in all flats
Ceiling plastering work in First floor is in completed
Laying of Electrical pipe and fixing metal box work in First floor is in progress
Ceiling plastering in stilt floor (Car parking) is completed
CLUB HOUSE
Earth work excavation is completed for Grade beam
Fabrication of steel work for grade beam is in progress
Column concreting up to grade beam level is completed