Photo Gallery

Photo Gallery

AUGUST 2019

BLOCK:I

  • Casting of Fourth Floor roof slab (terrace floor) is completed and curing work is in progress
  • Brick work in First floor is completed in all flats
  • Brick work up to lintel level in second floor is in progress
  • Ceiling and column plastering in stilt floor (Car parking) is completed

BLOCK:V

  • Column concreting for 49 Nos is completed in fourth floor, Fabrication of steel is completed for the remaining columns and shuttering work for the remaining columns in fourth floor is in progress
  • 50% of shuttering and fabrication of steel work for fourth floor roof slab is in progress
  • Brick work up to Lintel level in First floor is completed in all flats and Brick work above lintel level is in progress in two flats after casting of lintel concrete
  • Ceiling plastering in stilt floor (Car parking) is in progress

CLUB HOUSE

  • Earth work excavation is completed for column footings
  • Laying of foundation concrete in Plain Cement concrete for footings is completed
  • Laying of RCC Footing for Column is completed

INFRASTRUCTURE

  • Perimeter Compound wall work is in progress
JULY 2019

BLOCK:I

  • Column concreting for 56 Nos is completed in fourth floor and Fabrication of steel and shuttering work for the remaining columns in fourth floor is in progress.
  • 50% of shuttering work for fourth floor roof slab is completed and fabrication of steel work is in progress.
  • Brick work up to Lintel level in First floor is completed in all flats and Brick work above lintel level is in progress in two flats after casting of lintel concrete.
  • Fabrication of steel and shuttering work is in progress for casting of lintel for remaining flats in first floor
  • Brick work in second floor is in progress
  • Ceiling plastering in stilt floor (Car parking) is in progress

BLOCK: V

  • Casting of Third Floor roof slab is completed and curing work is in progress.
  • Brick work in First floor is in progress

CLUB HOUSE

  • Earth work excavation is completed for column footings
  • Laying of foundation concrete in Plain Cement concrete for 26 footings is completed and work is in progress for the remaining footings.
  • Laying of RCC for Column footing is completed for 16 columns and fabrication of steel for remaining footings and columns work is in progress.

INFRASTRUCTURE

  • Perimeter Compound wall work is in progress
JUNE-2019

BLOCK:I

  • Casting of Third Floor roof slab is completed and curing work is in progress
  • Brick work up to Lintel level in First floor is in progress.

BLOCK:V

  • Column concreting for 47 Nos is completed in third floor and Fabrication of steel and shuttering work for the remaining columns in third floor is in progress.
  • Third floor roof slab shuttering and fabrication of steel work is completed and laying of electrical pipe work is in progress for the 50% of slab area. Concreting is scheduled on 2nd July.
  • Shuttering work is in progress for the remaining 50% area

CLUB HOUSE

  • Earth work excavation is in progress

INFRASTRUCTURE

  • Perimeter Compound wall work is in progress
MAY -2019

BLOCK :I

  • Column concreting is completed in third floor.
  • Third floor roof slab shuttering work and fabrication of steel work is in progress for the 50% of slab area and Concreting is scheduled for Coming week.
  • Marking of brick work in First floor is in progress.

BLOCK :V

  • Second Floor roof slab curing work is in progress

INFRASTRUCTURE

  • Perimeter Compound wall work is in progress
APRIL -2019

Block I:

  • Casting of Second Floor roof slab is completed and curing work is in progress.

Block V:

  • Column concreting for 36 Nos is completed in second floor. Fabrication of steel work is completed for the remaining columns and shuttering & column concreting is in progress for the remaining columns in second floor.
  • Second floor roof slab shuttering work and fabrication of steel work is in progress for the 50% of slab area.

Infrastructure

  • Perimeter Compound wall work is in progress.
MARCH -2019

Block I:

  • Column concreting for 45 Nos is completed in second floor, Steel fabrication work is completed for the remaining columns and shuttering work is in progress for the remaining columns in second floor.
  • Second floor roof slab shuttering work is in progress.

Block V:

  • Casting of First Floor roof slab is completed.
  • Fabrication of steel work for columns in second floor is in progress.

Infrastructure

  • Perimeter Compound Wall work is in progress.
SEPEMBER-2019

BLOCK :I

  • Brick work up to lintel level in Third Floor is in Progress
  • Brick work up to lintel level in second floor is completed
  • Brick work in First floor is completed in all flats
  • Ceiling plastering work in First floor is completed
  • Laying of Electrical pipe and fixing metal box work in First floor is in progress
  • Ceiling and column plastering work in stilt floor (Car parking) is completed.

BLOCK : V

  • Casting of Fourth Floor roof slab (terrace floor) is completed
  • Brick work up to Lintel level in Third floor is in progress
  • Brick work up to Lintel level in second floor is in progress
  • Brick work in First floor is completed in all flats
  • Ceiling plastering work in First floor is in progress
  • Laying of Electrical pipe and fixing metal box work in First floor is in progress
  • Ceiling plastering in stilt floor (Car parking) is completed

CLUB HOUSE

  • Earth work excavation is completed for Grade beam
  • Fabrication of steel work for grade beam is in progress
  • Column concreting up to grade beam level is completed

INFRASTRUCTURE

  • Perimeter Compound wall work is in progress
OCTOBER - 2019

BLOCK - I

  • Brick work up to lintel level in Second and Third Floor is completed
  • Brick work upto lintel level in Fourth floor is in progress
  • Ceiling plastering work in First floor is completed
  • Laying of Electrical pipe and fixing metal box work in First floor is in progress
  • Wall plastering work in First floor is in progress
  • Ceiling and column plastering work in stilt floor (Car parking) is completed

BLOCK - V

  • Brick work up to Lintel level in Second and Third floor is in progress
  • Brick work in First floor is completed in all flats
  • Ceiling plastering work in First floor is in completed
  • Laying of Electrical pipe and fixing metal box work in First floor is in progress
  • Ceiling plastering in stilt floor (Car parking) is completed

CLUB HOUSE

  • Earth work excavation is completed for Grade beam
  • Fabrication of steel work for grade beam is in progress
  • Column concreting up to grade beam level is completed

Infrastructure

  • Perimeter Compound wall work is in progress