Photo Gallery

Photo Gallery

April - 2019

Block I

  • Casting of Second Floor roof slab is completed and curing work is in progress.

Block V

  • Column concreting for 36 Nos is completed in second floor. Fabrication of steel work is completed for the remaining columns and shuttering & column concreting is in progress for the remaining columns in second floor.
  • Second floor roof slab shuttering work and fabrication of steel work is in progress for the 50% of slab area.

Infrastructure

  • Perimeter Compound wall work is in progress.
March - 2019

Block I:

  • Column concreting for 45 Nos is completed in second floor, Steel fabrication work is completed for the remaining columns and shuttering work is in progress for the remaining columns in second floor.
  • Second floor roof slab shuttering work is in progress.

Block V:

  • Casting of First Floor roof slab is completed.
  • Fabrication of steel work for columns in second floor is in progress.

Infrastructure

  • Perimeter Compound Wall work is in progress.
MAY -2019

BLOCK :I

  • Column concreting is completed in third floor.
  • Third floor roof slab shuttering work and fabrication of steel work is in progress for the 50% of slab area and Concreting is scheduled for Coming week.
  • Marking of brick work in First floor is in progress.

BLOCK :V

  • Second Floor roof slab curing work is in progress

INFRASTRUCTURE

  • Perimeter Compound wall work is in progress