Photo Gallery

Photo Gallery

OLI PARAVATTUM - Dated on 15.01.2024

NALAM THARUM AANMIGA NERIMURAIGAL 1.1.2024

PHASE 1 COMPLETED

SEPTEMBER -2020

BLOCK - I

  • Internal Work · Toilet - Flush tank (concealed) fixing work is in progress for toilets
  • External Work
  • Brickwork in South side balcony and concreting work in the same area for Elevation is in progress
  • External putty work is progress in East and South side
  • Elevation plastering work is progress in West sides
  • Laying of clay tiles for Weathering proof over surki concrete is completed
  • Plumbing shaft pipe line work is in progress

BLOCK V

  • External Work
  • Brick work is progress for Elevation work in North side
  • Elevation plastering work is progress in West sides
  • Plastering work inside the Open to Sky (OTS) area is completed

CLUB HOUSE

  • Ground Floor
  • Internal plastering work is completed and curing work is in progress
  • First Floor · Brick work is in progress.

SEWAGE TREATMENT PLANT (STP)

  • Internal plastering for RCC wall work is in progress.
  • Roof slab shuttering work is in progress
AUGUST -2020

BLOCK - I

  • Fourth Floor · Internal putty work is completed.
  • External Work · South side balcony brick work and concreting work for elevation is in progress. · Brick work and Plastering work are in progress on Eastern side for elevation.
  • External Work · South side balcony brick work and concreting work for elevation is in progress. · Brick work and Plastering work are in progress on Eastern side for elevation.

BLOCK -V

  • Second Floor · Water proofing work for toilets is completed.
  • Third Floor · Internal Putty work is in progress.
  • External Work · Plastering work for the Lift and Open to Sky (OTS) area is in progress and the same for external areas to be commenced.

CLUB HOUSE

  • Ground Floor · Electrical wall cutting work and Laying of electrical pipe line work is in progress. · Internal plastering work is in progress.
  • Second Floor · Casting of second floor roof slab work is completed and curing work is in progress.

SEWAGE TREATMENT PLANT (STP)

  • RCC wall concreting up to 8'6" height is completed and steel shuttering work for the next level is completed. Concreting is scheduled on 07th September.
JULY-2020

BLOCK -1

  • Fourth Floor · Internal putty work is in progress. · Laying of pipe lines inside toilets is in progress
  • External work · South side balcony brick work and concreting work for elevation is in progress. · North side plastering work is completed. · Brick work is in progress on Eastern side for elevation.

BLOCK -5

  • Second Floor · Ceiling Plumbing line laying work (suspended plumbing works) inside the toilets is completed.
  • Third Floor · Internal plastering work is completed for flats and the same for corridor areas to be commenced.
  • Fourth Floor · Internal plastering work is in progress.

CLUB HOUSE

  • Ground Floor · Electrical wall cutting work and Laying of electrical pipe line work is in progress. · Internal plastering work is in progress.
  • Second Floor · Roof slab shuttering work is in progress.

SEWAGE TREATMENT PLANT (STP)

  • RCC wall concreting upto 3'0" height is completed and Fabrication of steel work and shuttering work is in progress for the remaining area.
JUNE -2020

BLOCK : 1

  • Third Floor · Internal and corridor area putty work is completed.
  • Fourth Floor · Internal plastering work for 7 flats is completed and the same for remaining flat and corridor work is in progress.
  • External work · 3 Nos of OTS area (Open To Sky) plastering work is completed. · OTS area (Open To Sky) white washing work is in progress. · South side balcony brick work and elevation work is in progress. · Plumbing work inside the shaft area is in progress.

BLOCK : 5

  • First Floor · Ceiling Plumbing line laying work (suspended plumbing works) inside the toilets is completed.
  • Second Floor · Internal Putty work is completed.
  • Third Floor · Internal plastering work is in progress
  • Fourth Floor · Laying of Electrical pipeline work is completed. · Internal plastering work is in progress.
  • Terrace Floor · Over Head water tank wall concreting work is completed. · Laying of weathering course with lime surkhi concrete is in progress.

CLUB HOUSE

  • Second Floor · Column concreting upto second floor roof is in progress.

SEWAGE TREATMENT PLANT

  • Earth work excavation work is completed. · Plain Cement concreting work is completed. · Footing concreting work is completed. · Consolidation work is in progress.
MAY -2020

BLOCK - I ;

  • First Floor • Water Proofing work is completed in toilets.
  • Second Floor • Water Proofing work is completed in toilets. • Entrance Door frames and bed room door frames fixing work is completed
  • Third Floor • Entrance Door frames and bed room door frames fixing work is in progress. • Ceiling Plumbing line laying work (suspended plumbing works) inside the toilets is completed. • Plumbing wall cutting and pipeline laying work in toilets is completed.
  • Terrace Floor Laying of Weathering course with surki lime concrete is in progress.

BLOCK : V

  • Ground Floor (Car parking Area) • Putty work is in progress.

CLUB HOUSE

  • Ground Floor: • Brick work is in progress
  • First Floor • Casting of (16 Feet height) roof slab concrete is completed and curing work is in progress.
  • Second Floor • Column concreting upto second floor roof is in progress
APRIL - 2020 - LOCKDOWN
MARCH 2020

BLOCK : I

  • Stilt Floor
  • White washing for ceiling and columns is completed and Putty work for ceiling is completed.
  • First Floor
  • Plumbing line laying work inside the toilets is in progress.
  • Second Floor
  • Plumbing line laying work inside the toilets is in progress.
  • First coat of putty work is completed
  • Third Floor
  • Internal plastering work is in progress
  • First coat of putty work is completed in four flats
  • Fourth Floor
  • Wall cutting work for laying electrical pipe line is in progress
  • Laying of Electrical pipe and fixing metal box work is in progress

BLOCK - 5

  • First Floor
  • First Floor - Internal Plastering work is completed.
  • Second floor - Internal plastering work is in progress
  • Third Floor - Wall cutting and laying of electrical pipe line work is completed
  • Fourth Floor - Brick work up to roof level is completed.
  • Terrace - Brick work for Parapet Wall is completed.
  • Shuttering and fabrication of steel for Staircase Head room is in progress.

BLOCK : II

  • Grade beam concreting work is in progress
  • Raising of Columns upto stilt floor roof level is in progress
  • Brick Work upto Basement level is in progress
  • Refilling inside the basement and consolidation work is in progress
  • Laying of Plain cement Concrete for flooring is in progress

Club House

  • Ground Floor - Brick work is in progress. - Lintel concreting work is in progress.
  • First Floor - Casting of First floor roof slab (upto 14 feet height first level) is completed and curing work is in progress. - Wall concreting for swimming pool is completed and curing work is in progress.
  • Second Floor - Raising of Columns upto second floor roof level is in progress
FEBRUARY -2020

BLOCK : I

  • First Floor - Plumbing line laying work inside the toilets is in progress. First coat of putty work is completed
  • External Elevation work is in progress
  • Second Floor - First coat of putty work is completed
  • Third Floor - Internal plastering work is in progress

BLOCK :V

  • First Floor - Internal Plastering work is completed
  • Second floor -Internal plastering work is in progress
  • Third Floor - Wall cutting and laying of electrical pipe line work is in progress
  • Terrace - Brick work for Parapet Wall is in progress

BLOCK :II

  • Column footing work is fully completed
  • Grade beam concreting work is in progress
  • Raising of Columns upto stilt floor roof level is in progress
  • Brick Work upto Basement level is in progress

CLUB HOUSE

  • Ground Floor - Brick work is in progress.
  • First Floor - Shuttering and fabrication of steel work for roof slab is in progress
  • Kindly note that Concreting of first floor roof slab is scheduled on 4th March 2020
JANUARY- 2020

BLOCK-I

  • • First Floor - Wall plastering work is completed. Plumbing line laying work inside the toilets is in progress
  • Second Floor - Electrical Box fixing work is completed and internal plastering work is in progress
  • Third Floor - Wall cutting and laying of electrical pipe line work is in progress.
  • Fourth Floor - Brick work upto roof level is completed
  • Terrace - Parapet Wall brickwork is completed. Shuttering and fabrication of steel for lift room and staircase head room is in progress.

BLOCK- V

  • First Floor - Wall Plastering work is completed
  • Second Floor - Electrical Box fixing and Internal plastering work is in progress
  • Fourth Floor - Lintel concreting work and brick work above lintel is in progress.
  • Terrace - Brick work for Parapet Wall, Lift and staircase head room is in progress

BLOCK -II

  • • Ground Level - Refilling of soil and consolidation work inside column footing pit is in progress
  • Brick on edge for grade beam is in progress.

CLUB HOUSE

  • Ground Floor - Casting of Ground floor roof Slab is completed and curring work is in progress.
  • First Floor - Raising of Columns upto first floor roof level is in progress
AUGUST 2019

BLOCK:I

  • Casting of Fourth Floor roof slab (terrace floor) is completed and curing work is in progress
  • Brick work in First floor is completed in all flats
  • Brick work up to lintel level in second floor is in progress
  • Ceiling and column plastering in stilt floor (Car parking) is completed

BLOCK:V

  • Column concreting for 49 Nos is completed in fourth floor, Fabrication of steel is completed for the remaining columns and shuttering work for the remaining columns in fourth floor is in progress
  • 50% of shuttering and fabrication of steel work for fourth floor roof slab is in progress
  • Brick work up to Lintel level in First floor is completed in all flats and Brick work above lintel level is in progress in two flats after casting of lintel concrete
  • Ceiling plastering in stilt floor (Car parking) is in progress

CLUB HOUSE

  • Earth work excavation is completed for column footings
  • Laying of foundation concrete in Plain Cement concrete for footings is completed
  • Laying of RCC Footing for Column is completed

INFRASTRUCTURE

  • Perimeter Compound wall work is in progress
JULY 2019

BLOCK:I

  • Column concreting for 56 Nos is completed in fourth floor and Fabrication of steel and shuttering work for the remaining columns in fourth floor is in progress.
  • 50% of shuttering work for fourth floor roof slab is completed and fabrication of steel work is in progress.
  • Brick work up to Lintel level in First floor is completed in all flats and Brick work above lintel level is in progress in two flats after casting of lintel concrete.
  • Fabrication of steel and shuttering work is in progress for casting of lintel for remaining flats in first floor
  • Brick work in second floor is in progress
  • Ceiling plastering in stilt floor (Car parking) is in progress

BLOCK: V

  • Casting of Third Floor roof slab is completed and curing work is in progress.
  • Brick work in First floor is in progress

CLUB HOUSE

  • Earth work excavation is completed for column footings
  • Laying of foundation concrete in Plain Cement concrete for 26 footings is completed and work is in progress for the remaining footings.
  • Laying of RCC for Column footing is completed for 16 columns and fabrication of steel for remaining footings and columns work is in progress.

INFRASTRUCTURE

  • Perimeter Compound wall work is in progress
JUNE-2019

BLOCK:I

  • Casting of Third Floor roof slab is completed and curing work is in progress
  • Brick work up to Lintel level in First floor is in progress.

BLOCK:V

  • Column concreting for 47 Nos is completed in third floor and Fabrication of steel and shuttering work for the remaining columns in third floor is in progress.
  • Third floor roof slab shuttering and fabrication of steel work is completed and laying of electrical pipe work is in progress for the 50% of slab area. Concreting is scheduled on 2nd July.
  • Shuttering work is in progress for the remaining 50% area

CLUB HOUSE

  • Earth work excavation is in progress

INFRASTRUCTURE

  • Perimeter Compound wall work is in progress
MAY -2019

BLOCK :I

  • Column concreting is completed in third floor.
  • Third floor roof slab shuttering work and fabrication of steel work is in progress for the 50% of slab area and Concreting is scheduled for Coming week.
  • Marking of brick work in First floor is in progress.

BLOCK :V

  • Second Floor roof slab curing work is in progress

INFRASTRUCTURE

  • Perimeter Compound wall work is in progress
APRIL -2019

Block I:

  • Casting of Second Floor roof slab is completed and curing work is in progress.

BLOCK :V

  • Second Floor roof slab curing work is in progress

INFRASTRUCTURE

  • Perimeter Compound wall work is in progress
APRIL -2019

Block I:

  • Casting of Second Floor roof slab is completed and curing work is in progress.

Block V:

  • Casting of First Floor roof slab is completed.
  • Fabrication of steel work for columns in second floor is in progress.

Infrastructure

  • Perimeter Compound Wall work is in progress.
SEPEMBER-2019

BLOCK :I

  • Brick work up to lintel level in Third Floor is in Progress
  • Brick work up to lintel level in second floor is completed
  • Brick work in First floor is completed in all flats
  • Ceiling plastering work in First floor is completed
  • Laying of Electrical pipe and fixing metal box work in First floor is in progress
  • Ceiling and column plastering work in stilt floor (Car parking) is completed.

BLOCK : V

  • Casting of Fourth Floor roof slab (terrace floor) is completed
  • Brick work up to Lintel level in Third floor is in progress
  • Brick work up to Lintel level in second floor is in progress
  • Brick work in First floor is completed in all flats
  • Ceiling plastering work in First floor is in progress
  • Laying of Electrical pipe and fixing metal box work in First floor is in progress
  • Ceiling plastering in stilt floor (Car parking) is completed

CLUB HOUSE

  • Earth work excavation is completed for Grade beam
  • Fabrication of steel work for grade beam is in progress
  • Column concreting up to grade beam level is completed

INFRASTRUCTURE

  • Perimeter Compound wall work is in progress
OCTOBER - 2019

BLOCK - I

  • Brick work up to lintel level in Second and Third Floor is completed
  • Brick work upto lintel level in Fourth floor is in progress
  • Ceiling plastering work in First floor is completed
  • Laying of Electrical pipe and fixing metal box work in First floor is in progress
  • Wall plastering work in First floor is in progress
  • Ceiling and column plastering work in stilt floor (Car parking) is completed

BLOCK - V

  • Brick work up to Lintel level in Second and Third floor is in progress
  • Brick work in First floor is completed in all flats
  • Ceiling plastering work in First floor is in completed
  • Laying of Electrical pipe and fixing metal box work in First floor is in progress
  • Ceiling plastering in stilt floor (Car parking) is completed

CLUB HOUSE

  • Earth work excavation is completed for Grade beam
  • Fabrication of steel work for grade beam is in progress
  • Column concreting up to grade beam level is completed

Infrastructure

  • Perimeter Compound wall work is in progress